€264,699 | ||
|
€ 27,171. | ||
| Architectural services construction document | |||
| & construction oversight Sub-total Shelters (A) | € 20,000. | € 311,870. | |
|
|||
| 630 meters @ €60./ meter | € 37,800. | ||
|
|||
| 3 pair bi-fold steel gates.
Sub-total perimter security (B) |
€ 9,450 | ||
| €47,250 | |||
|
|||
| Writer/sign designer w/ interpretation | € 1,050 | ||
|
€ 500 | ||
| € 360 | |||
| € 164 | |||
| € 2,074. | |||
|
|||
| 2 weeks, 2 workmen | € 3,726 | € 3,726 | |
15% of construction cost ( AI,AII,BI,BII,CII,CIII ) |
|||
| € 338,980. (15%) | € 50,997. | ||
| Sub-total project management | € 50,997 | ||
|
|||
| 10% of construction cost ( AI,AII,BI,BII,CII,CIII ) | |||
| € 338.980. (10%) | € 33,898 | ||
| Sub-total contingency | € 33,898 | ||
| Total Phase II conservation & development 2009 | € 449,815 | ||
| (US $ 603,697) | |||